Development finance calculator
What a development facility really costs, drawn down the way it is actually drawn
Every simple development calculator gets the same thing wrong. The build tranche is not outstanding for the whole term: it is drawn monthly against measured progress, so the interest on it is roughly half what a flat calculation suggests. Charging the full facility for the full term overstates the cost by a third on a typical scheme, and pricing a site off that number loses deals that were viable. This draws it down properly and shows both figures.
For: Ground up, or a conversion drawn down against the work
Lender caps
If the programme slips£22,644
Where these figures come from
Rates. UK development finance runs 0.65% to 1.10% a month in 2026, roughly 8% to 13% a year. Established developers on residential ground-up schemes sit at 0.65% to 0.90%; higher leverage, less experience or a complex structure reaches 1.10% and above. Lenders price at base rate plus three to five points on a monthly rolled basis.
Caps. Most lenders advance up to 65% of GDV, some to 70% for stronger applications, and 85% to 90% of total cost with the GDV cap taking precedence. The day one land advance is capped separately at 60% to 70% of site value. First-time developers typically face 85% loan to cost and 65% loan to GDV rather than the standard limits, plus higher rates and more intensive monitoring.
Profit. Most development lenders require a projected profit of 17.5% to 20% on gross development value, which is also the RICS viability benchmark for a residential scheme.
The drawdown model. The land advance is treated as outstanding for the full term and compounding. The build tranche is split into equal monthly slices across the build period, each compounding for the time it is actually outstanding, and the results are summed rather than averaged.
Interest is rolled up rather than serviced on almost every development facility, so it compounds and it comes out of the profit at the end rather than out of cash flow along the way. Build drawdowns are made in arrears against a monitoring surveyor's certificate, which means you fund each stage before you are reimbursed for it: a scheme with no working capital stalls even with a fully agreed facility. The lender's valuer sets the GDV, not you, and a valuation below your figure tightens both caps at once. An overrun is the commonest thing that goes wrong and the lender is under no obligation to extend. Development finance is arranged through a regulated broker or lender. An estimate, not advice.