New build calculator
What building it from nothing costs, from the ground to the handover
A new dwelling is the one job where the tax works in your favour: the construction is zero rated for VAT, which is worth a fifth of the bill against any refurbishment of the same size. Against that, the site costs that do not exist on an existing building are real money: the services, the drainage, the roads, the warranty and the planning obligations. This prices all of it.
For: A new build from scratch, or a demolish and rebuild
Site costs
Fees, consents and the warranty
Where these figures come from
Build rates. UK new build at 2026 prices: budget £1,800 to £2,200 a square metre, mid range £2,200 to £2,800, high end £2,800 to £3,500 and above. An average self build is likely to cost £2,500 to £3,000. Regionally, from about £1,900 a square metre for a standard specification house in the north to £4,500 or more for a bespoke architect-designed house in London. These are core building work and exclude land, professional fees and external works.
Fees. A full planning application for a new dwelling is £610 per dwelling below ten from 1 April 2026, and £659 each for ten to fifty. Structural warranties run ten years and are effectively required by lenders.
VAT. The construction of a new dwelling is zero rated, including on a site cleared to slab level by demolition. Professional fees are standard rated. Self-builders reclaim VAT on materials under the DIY Housebuilders Scheme in a single claim within six months of completion.
CIL is charged per square metre of new floorspace under each charging authority's published schedule and is payable on commencement. Self-build relief is available and must be claimed, and acknowledged, before work starts.
Excludes the land, the stamp duty on it and the finance. Site costs are where new builds overspend, and the only way to know about them before committing is a ground investigation, which costs a few thousand pounds and routinely saves tens of thousands. Services connections are quoted by the network operators rather than by your builder and the lead times run to months, so they belong on the programme from week one. The self build VAT reclaim is a single claim made within six months of completion and it depends entirely on holding the invoices, so keep them from the first delivery. CIL self-build relief has to be claimed and acknowledged before work commences; starting first makes the whole levy payable and there is no discretion in it. An estimate, not a quotation.